Project Transportation by NAWINIA Team

The NAWINIA company transported the equipment of the “M-500 Methanol” complex for integrated chemical company “Shchyokinoazot” by four stage.

Task is to deliver equipment that weight 292 tons from Zlate-Gori to Pervomayskiy in 35 days with minimization of expenses.

First stage - was road transportation on modular trailers from producers in Czech Republic to port in Bratislava,Slovenia. First stage took only 2 days.

Second stage - river transportation from the port of Bratislava to the port of Antwerp through the Danube, Main and Rhine rivers. Transit time of transition to the barge - towing structure – 20 days.

Sea transportation from port of Antwerp to port of Saint-Petersburg was third stage of transportation. The package weighing 118. 4 tons was shipped on the vessel by a crane method, and packages with a smaller weight were shipped by roll trailers. Transportation time was - 5 days. 

Final stage of transportation became a road transportation by modular trailers and lowboy trailer from Petrolesport to Saint-Petersburg on Tulskaya Square. We passed more than 1000 km in 3 days and successfully finished project in time.

From the output of the equipment from the factory to arrival on the building site there passed 35 days.